STAFF REPORT | The Municipal Council announced yesterday that renovation work on three footbridges had been completed, at a total cost of 310 million yuan. The renovation included replacing exterior wall panels, installing lighting, and resurfacing the ground. The council described the works as "improving the urban walking environment."
A reporter for this newspaper visited one of the footbridges in Central yesterday. The exterior walls had indeed been changed to light gray, and the ground was newly paved. At the escalators at the two ends of the footbridge, one side had an "Out of service" notice posted, dated December last year.
This newspaper tried the maintenance contractor's phone number on the notice three times: twice there was no answer, and once it went to voicemail.
Mr Chan, a member of the public who works near the footbridge, said, "I remember this escalator hasn't run since last year." "I don't object to changing the color, but I go up and down six times a day," he said. The footbridge stairs have 37 steps.
The Municipal Council replied to this newspaper that the replacement of the escalators was a separate project, "expected to begin in the first quarter of next year." A spokesman said the renovation works and the escalator repairs "come under different funding allocations."
This newspaper reviewed documents submitted by the Municipal Council last year; the scope of the footbridge renovation works included "ancillary facilities." The documents did not further specify whether "ancillary facilities" included the escalators.
An engineering industry figure pointed out that exterior wall and ground works generally cost several million yuan per footbridge, and 300 million yuan "clearly includes other items." This newspaper again asked the Municipal Council for a breakdown of the cost but had received no reply by deadline.